Image Source : TWITTER/@NHSRCL Construction of tunnel under bullet train project is underway
National High-Speed Rail Corporation Limited (NHSRCL) on Friday said Afcons Infrastructure Limited quoted the lower amount among two technically qualified financial bids for the construction of a 21-kilometre tunnel, including 7 kilometres under the sea, as part of the Mumbai-Ahmedabad bullet train project.
NHRSCL said it had received bids from Afcons Infrastructure Limited and Larsen & Toubro Limited for constructing the tunnel that will stretch from the proposed underground station at Bandra Kurla Complex in Mumbai to Shilphata in neighboring Thane district.
New Austrian Tunnelling Method being used
“The tunnel will be a single-tube twin-track tunnel having a diameter of 13.1 metres. Out of 20.37 km, 15.42 km of tunnelling will be carried out with three TBMs (Tunnel Boring Machine) and the remaining 4.96 km will be built using New Austrian Tunnelling Method (NATM). The depth of the tunnel will vary from 25 metres to 65 metres,” the NHRSCL said in a release.
“The tunnel will cross Thane creek and the survey work under the creek was done using underwater static refraction technique.
The deepest construction point will be 114 metres below Parsik Hill near Shilphata,” an NHSRCL spokesperson said.
TBMS with a cutter head of 13.1 metre diameter will be used, much larger than the 5-6 metre diameter cutter heads used for metro rail systems etc, the spokesperson added.
Total cost Rs around 1 lakh crore. The high speed corridor between Mumbai and Ahmedabad is coming up at a cost of Rs 1.08 lakh crore.
While the dominant part of the cost is covered by a loan from Japan, the rest will be contributed by the Union government and the governments of Maharashtra and Gujarat.
(With PTI input)
Also read- PIB row: ‘Fact Check will not be done by PIB, Centre yet to decide’, clarifies Union Min Chandrashekhar
Latest Business News
Source link